Priority Room Description Cost - Labor Cost - Parts Duration Dates of work Worker(s) Equipment,
supplies & parts
Comments
1 Basement Replace electrical panel & power entrance $500 $550 3 days 8/23-8/25 Mike Electrical panel  
1 Bedrooms Light switch needs replacing $50 $25 2 hours   Mike    
1 Basement Replace furnace filter $0 $20 1 hour   Us Filter  
1 Bathroom Prep & paint trim & cupboards $0 $25 1 day 8/24-8/25 Corinne & friends Tape, brushes, paint, sandpaper, deglosser  
1 Bathroom Replace shower head $0 $50 1 hour   Us Shower head, wrench  
1 Bedrooms Prep & paint trim (& walls?) $0 $25 3 days 8/24-8/25 Corinne & friends Tape, brushes, paint, sandpaper, deglosser  
1 Bedrooms Pull up carpet $0 $0 1 day 8/20-8/21 Us Carpet knives, crowbar/hammer  
1 Bedrooms Refinish hardwood floors $800 $0 2 days 9/8-9/10 Refinisher N/A  
1 Doors Re-key or replace locks on 3 doors $100 $150 1 hour   Locksmith N/A Tied to glass door in kitchen
1 Kitchen Replace/fix lock on sliding glass door $50 $10 1 hour   Locksmith N/A  
1 Kitchen Install dishwasher $0 $600 3-4 days 8/26-8/29 Tim & Corinne Saw, dishwasher If it fits; have to run water & power
1 Outside Dig trenches from gutters $100 $100 2 days   TJ? Shovel, pipe, "ditcher" How much to rent a ditcher? Could we get it up the stairs?
1 Whole house Install smoke detectors $0 $50 0.5 days     Ladder, smoke detectors  
1 Roof Herbicide on roof to kill moss $0 $20 0.5 days   Benjamin Ladder, herbicide/zinc strips from Tim  
    TOTAL PRI 1 $1,600 $1,605          
    $3,205              
                   
2 Bathroom Replace light fixture above sink $100 $150 1 day   Mike/Tim Fixture  
2 Bathroom Replace shower rod with curved rod $0 $50 1 day   Us Shower rod  
2 Kitchen Replace electrical range with gas range $120 $550 1 hour 9/5 Gas company Gas range Installation of new range must be done after new countertops are finished! Might be able to exchange electric range
2 Kitchen Tile countertops $0 $500 7 days 8/26-8/26,
8/31-9/5
Tim, Corinne & Mike Tile, tile cutter, plywood, saw Replace countertops down to plywood; Tied to dishwasher
2 Whole house Replace electrical outlets $100 $150 1 day   Mike Outlets GFI's where applicable
2 Fireplace Full out fireplace insert $0 $0 .5 day   Benjamin & friends    
2 Fireplace Put hat on  (& clean) chimney $300 $100     Chimney guy N/A  
2 Fireplace Fix flu $100 $100     Chimney guy    
2 Outside Install porch swing $0 $200 1 day   Us & Tim Stud finder, drill, chain, swing  
    TOTAL PRI 2 $720 $1,800          
    $2,520   TOTAL PRI 1 + 2 $5,725        
                   
3 Basement Run CAT-6 cable $600 $300     Mike Conduits, panels  
3 Basement Run coax cable $600 $300     Mike Coax cable, panels  
3 Basement Run phone lines $600 $200     Mike Phone line, panels  
3 Bathroom Replace sink $200 $200     ? Sink, wrench  
3 Bathroom Replace/paint/refinish medicine cabinet $0 $25     Us Tape, brushes, paint, sandpaper, deglosser, new knob  
3 Kitchen Paint cabinets $0 $150     Us Tape, brushes, paint, sandpaper, deglosser  
    TOTAL PRI 3 $2,000 $1,175          
    $3,175   TOTAL PRI 1+2+3 $8,900        
                   
4 Attic Replace knob-and-tube wiring         Mike    
4 Basement Framing          Contractor    
4 Basement Install Pergo flooring         Us    
4 Basement Replace knob-and-tube wiring         Mike    
4 Basement Sheet rocking         Contractor    
4 Bathroom Replace fixtures         Us    
4 Kitchen Extend island              
4 Kitchen Install French doors              
4 Whole house Paint walls $0       Us    
4 Crawl space I-bolts & sil plate              
4 Crawl space Foundation patch/caulc/fix              
    TOTAL PRI 4 $0 $0 $0        
                   
5 Bedroom Replace blue blinds              
5 Crawl space Foundation repair              
5 Crawl space Raise floor              
5 Crawl space Finish crawl space              
    TOTAL PRI 5 $0 $0 $0